Browns Ferry Nuclear Plant Units 1, 2 and 3 – Subsequent License Renewal: NRC subsequent licence renewal review for Tennessee Valley Authority — issued, 20.7 months from docketing to decision. Sourced dates and schedule.
Background: NRC reactor licensing process, explained · The ADVANCE Act, explained: what changed and where the NRC stands
Current state
| Type | Subsequent licence renewal |
| Outcome | Issued |
| Applicant | Tennessee Valley Authority |
| Facility | Browns Ferry Nuclear Plant (Browns Ferry 1, Browns Ferry 2, Browns Ferry 3) |
| Docket | 50-259, 50-260, 50-296 |
| Submitted | 2024-01-19 |
| Docketed (accepted for review) | 2024-03-21 |
| NRC planned schedule | — |
| NRC target date | 2025-10-15 |
| Final safety evaluation | 2025-07-18 |
| Decision | 2025-12-11 |
| Review time (docketed → decision) | 20.7 mo |
| Submitted → decision | 22.7 mo |
| NRC-reported review duration | — |
| NRC-reported resources vs estimate | — |
Review time is measured in average months from the date the NRC docketed the application to the decision. The NRC's own reported durations may measure to the final safety evaluation instead.
Notes
SLR status page lists 'Application Received 01/09/2024'; the FR notices and the plant page say January 19, 2024. Used 2024-01-19 (status-page value looks like a typo). Decided after the EO-driven acceleration era began but missed its accelerated Oct 15, 2025 target by ~2 months; fetched sources give no reason. No FR notice establishing a Licensing Board was found for this application in an FR API search. NRC decision target: originally 2026-01, latest 2025-10-15. Schedule: Archived page (last updated March 25, 2024; also Feb and June 2025) shows decision target January 2026; Revised Schedule Letters dated February 6, 2025 and August 7, 2025; current page shows target October 15, 2025; actual December 11, 2025 (later than the accelerated target, earlier than the original). The August 7, 2025 letter itself (ML25203A010) returned HTTP 403 and was not read.
Timeline
- 2024-01-19 — Application submitted. (source)
- 2024-03-21 — FR notice of acceptance and opportunity for hearing. (source)
- 2025-02-06 — Revised schedule letter. (source)
- 2025-07-18 — Final safety evaluation issued. (source)
- 2025-07-18 — Final safety evaluation issued. (source)
- 2025-08-07 — Revised schedule letter (target decision Oct 15, 2025). (source)
- 2025-08-21 — Final SEIS issued. (source)
- 2025-12-11 — Subsequent renewed licenses DPR-33, DPR-52, DPR-68 issued. (source)
- 2025-12-11 — Issued. (source)
The timeline is append-only: corrections are added as new entries. See the NNN Data License Terms for reuse of the event history.
Also tracked
NNN coverage
About Tennessee Valley Authority
- NRC approves TVA’s Clinch River BWRX-300 permit 2026-10-01
- NNN Daily Brief — July 12, 2026 2026-07-12
- TVA's 2026 IRP puts advanced nuclear in the grid plan 2026-07-12
- The 7 nuclear stories that mattered this week 2026-10-03
- Nuclear power for data centers, explained: every deal tracked 2026-10-01
- Bechtel splits with TerraPower on Natrium, files 200-job WARN notice 2026-09-20
Related reviews
- Clinch River Nuclear Unit 1 (BWRX-300) construction permit Issued · 14.7 mo
- Clinch River Nuclear Site early site permit (ESP-006) Issued · 35.6 mo
- R.E. Ginna Nuclear Power Plant – Subsequent License Renewal Under review · —
- Cooper Nuclear Station – Subsequent License Renewal Under review · —
- Nine Mile Point Nuclear Station Unit 1 – Subsequent License Renewal Under review · —
- Edwin I. Hatch Nuclear Plant Units 1 and 2 – Subsequent License Renewal Issued · 11.9 mo
- H.B. Robinson Steam Electric Plant Unit 2 – Subsequent License Renewal Issued · 11.8 mo
- Dresden Nuclear Power Station Units 2 and 3 – Subsequent License Renewal Issued · 18.1 mo
See all 75 reviews in the NRC Licensing Review Tracker →
Sources
- https://www.nrc.gov/licensing-applications/power-reactor-licensing/browns-ferry-nuclear-plant-units-1-2-and-3-subsequent-license-renewal-application
- https://www.federalregister.gov/documents/2024/02/08/2024-02611
- https://www.federalregister.gov/documents/2024/03/21/2024-06047
- https://www.federalregister.gov/documents/2025/12/16/2025-22840
- https://web.archive.org/web/20240406/https://www.nrc.gov/reactors/operating/licensing/renewal/applications/browns-ferry-subsequent.html
- https://web.archive.org/web/20250717/https://www.nrc.gov/reactors/operating/licensing/renewal/applications/browns-ferry-subsequent.html
- https://www.nrc.gov/licensing-applications/operating-reactor-licensing/reactor-license-renewal/status-subsequent-license-renewal-applications