St. Lucie Plant Units 1 and 2 – Subsequent License Renewal

Issued · Subsequent licence renewal · Operating fleet

St. Lucie Plant Units 1 and 2 – Subsequent License Renewal: NRC subsequent licence renewal review for Florida Power and Light Company — issued, 55.1 months from docketing to decision. Sourced dates and schedule.

Background: NRC reactor licensing process, explained · The ADVANCE Act, explained: what changed and where the NRC stands

Current state

TypeSubsequent licence renewal
OutcomeIssued
ApplicantFlorida Power and Light Company
FacilitySt. Lucie Plant (St. Lucie 1, St. Lucie 2)
Docket50-335, 50-389
Submitted2021-08-03
Docketed (accepted for review)2021-09-24
NRC planned schedule—
NRC target date—
Final safety evaluation2023-07-21
Decision2026-04-28
Review time (docketed → decision)55.1 mo
Submitted → decision56.8 mo
NRC-reported review duration—
NRC-reported resources vs estimate—

Review time is measured in average months from the date the NRC docketed the application to the decision. The NRC's own reported durations may measure to the final safety evaluation instead.

Notes

Longest SLR in the set (~57 months), mostly waiting on the post-CLI-22 environmental review; safety review was complete in July 2023. The SLR status page lists 'Date Entering Subsequent Period of Extended Operation' 03/01/2056 and 04/06/2063 — these are the new license expiration dates (per News Release 26-049), so that column is mislabeled for this row. Whether the final schedule was compressed for EO 14300 is not stated in fetched sources. NRC decision target: originally 2023-07, latest 2026-04. Schedule: Original target 07/2023 (final SER 12/2022); affected by Feb 2022 GEIS orders; current page shows 04/2026; actual 04/28/2026. Intermediate schedules were not retrieved (Wayback fetches failed).

Timeline

  • 2021-08-03 — Application submitted. (source)
  • 2021-09-24 — NRC letter: acceptable for docketing. (source)
  • 2021-09-29 — FR notice of acceptance and opportunity for hearing. (source)
  • 2022-02-24 — Commission GEIS orders affect review. (source)
  • 2023-07-21 — Safety evaluation issued (Rev. 1 2023-09-01). (source)
  • 2023-07-21 — Final safety evaluation issued. (source)
  • 2025-12-19 — Draft SEIS issued. (source)
  • 2026-03-13 — Final SEIS issued. (source)
  • 2026-04-28 — Subsequent renewed licenses DPR-67 and NPF-16 issued. (source)
  • 2026-04-28 — Issued. (source)

The timeline is append-only: corrections are added as new entries. See the NNN Data License Terms for reuse of the event history.

NNN coverage

About NextEra Energy

Related reviews

See all 75 reviews in the NRC Licensing Review Tracker →

Sources

  1. https://www.nrc.gov/licensing-applications/power-reactor-licensing/st-lucie-plant-units-1-2-subsequent-license-renewal-application
  2. https://www.federalregister.gov/documents/2021/08/16/2021-17416
  3. https://www.federalregister.gov/documents/2021/09/29/2021-21168
  4. https://www.federalregister.gov/documents/2026/05/01/2026-08551
  5. https://www.nrc.gov/sites/default/files/cdn/doc-collection-news/2026/26-049.pdf
  6. https://web.archive.org/web/20211018/https://www.nrc.gov/reactors/operating/licensing/renewal/applications/st-lucie-subsequent.html
  7. https://www.nrc.gov/licensing-applications/operating-reactor-licensing/reactor-license-renewal/status-subsequent-license-renewal-applications