Oskarshamn Units 1 and 2

Active dismantling · Sweden · Immediate dismantling

OKG's owners decided in 2015 to close Oskarshamn 1 and 2 early; O2 has been shut since 2016 and O1 since 2017, with Oskarshamn 3 still running. Reactor internals were segmented in 2018-2019, large-scale dismantling started in 2020, and the reactor pressure vessels were fully cut up by February 2025.

New to decommissioning? The nuclear decommissioning market in 2026: size, players, pipeline

Current state

StatusActive dismantling
CountrySweden
LocationOskarshamn, Kalmar
SiteOskarshamn
UnitsO1, O2
Unit count2
Reactor typesBWR
Owner / licenseeOKG AB (Uniper)
Decommissioning contractorUNNU consortium (NUKEM/Uniper Nuclear Services)
StrategyImmediate dismantling
Final shutdown2017
Decommissioning start2018
Target completion2028
Spent fuelNo fuel left at O1 and O2 since autumn 2018.

Notes

target 2028 = SSM's ~8-year estimate from 2020.

Timeline

  • 2015 — OKG's owners decided to close O1 and O2 early. (source)
  • 2017-12 — O2 was defuelled. (source)
  • 2018 — Cutting of O2 reactor internals began. (source)
  • 2020 — Large-scale dismantling and demolition of contaminated systems and buildings began. (source)
  • 2025-02-07 — The final reactor pressure vessel dismantling at Oskarshamn was reported complete. (source)

The timeline is append-only: corrections are added as new entries. Stated targets appear in the current-state table, never as milestones.

NNN coverage

About Oskarshamn Nuclear Power Plant

Related sites

See all 72 sites in the Nuclear Decommissioning Tracker →

Sources

  1. Dismantling and demolition — OKG (primary), checked 2026-10-11
  2. Anläggningar under avveckling — Swedish Radiation Safety Authority (SSM) (primary), checked 2026-10-11
  3. NUKEM and UNS dismantle final RPV at Sweden's Oskarshamn — ANS Nuclear Newswire, checked 2026-10-11