Tianwan-7

VVER-1200 · 1,110 MWe · Under construction · commercial operation est. 2026

Current state

StatusUnder construction
DesignVVER-1200 (PWR)
Net capacity1,110 MWe
CountryChina
VendorRosatom
Owner / operatorCNNC (JNPC)
Construction start2021-05-19
Original COD target—
Current COD estimate2026
Schedule slippage—

Notes

Fuel-loading date conflict flagged 2026-09-28: NucNet reported loading *completed* 2026-08-03 while CNNC via WNN/NEI says the *first* assembly entered the core 2026-08-12 (fuel supplied by TVEL/NZKhK under the units 7&8 contract) — treat Aug-12 as start, completion date unconfirmed. Unit 7 COD 2026 requires criticality + grid + tests still ahead; at risk — watch.

Milestone log

  • 2021-05-19 — Construction start (first concrete) (source)
  • 2026-06-16 — Listed as under construction in the WNA world table, grid connection estimated 2026 (source)
  • 2026-08-03 — First fuel loading completed; criticality and grid connection to follow (source)

The milestone log is append-only: corrections are recorded as new entries, never rewrites. Full history via /api/v1/changes.

NNN coverage

About Tianwan-7

On the VVER-1200 design

Sources

  1. https://world-nuclear.org/information-library/current-and-future-generation/plans-for-new-reactors-worldwide
  2. https://pris.iaea.org/pris/
  3. https://pris.iaea.org/PRIS/CountryStatistics/CountryDetails.aspx?current=CN
  4. https://www.nucnet.org/news/china-completes-first-fuel-loading-at-tianwan-7-nuclear-plant-8-3-2026