Clinch River Nuclear Site early site permit (ESP-006)

Issued · Early site permit · New reactors

Clinch River Nuclear Site early site permit (ESP-006): NRC early site permit review for Tennessee Valley Authority — issued, 35.6 months from docketing to decision. Sourced dates and schedule.

Background: NRC reactor licensing process, explained · The ADVANCE Act, explained: what changed and where the NRC stands

Current state

TypeEarly site permit
OutcomeIssued
ApplicantTennessee Valley Authority
FacilityClinch River Nuclear Site (Oak Ridge, Tennessee)
Docket52-047
Submitted2016-05-12
Docketed (accepted for review)2016-12-30
NRC planned schedule—
NRC target date—
Final safety evaluation2019-06-14
Decision2019-12-19
Review time (docketed → decision)35.6 mo
Submitted → decision43.2 mo
NRC-reported review duration—
NRC-reported resources vs estimate—

Review time is measured in average months from the date the NRC docketed the application to the decision. The NRC's own reported durations may measure to the final safety evaluation instead.

Notes

Pre-ADVANCE baseline. Supplemental information after the May 2016 submittal delayed docketing ~7.5 months.

Timeline

  • 2016-05-12 — Application received: “The NRC received the ESP application on May 12, 2016, and docketed it on December 30, 2016.” (source)
  • 2016-12-30 — Accepted for review (docketed): “The NRC received the ESP application on May 12, 2016, and docketed it on December 30, 2016.” (source)
  • 2019-06-14 — Final safety evaluation issued. (source)
  • 2019-08-14 — Commission mandatory hearing. (source)
  • 2019-12-19 — Issued: “Accordingly, the early site permit (ESP-006) was issued on December 19, 2019 and became effective immediately.” (source)

The timeline is append-only: corrections are added as new entries. See the NNN Data License Terms for reuse of the event history.

NNN coverage

About Clinch River site

About Tennessee Valley Authority

Related reviews

See all 75 reviews in the NRC Licensing Review Tracker →

Sources

  1. https://www.nrc.gov/facilities-safety/new-reactors/large-light-water-reactors/early-site-permit-applications-for-new-reactors/clinch-river-nuclear-site
  2. https://www.federalregister.gov/d/2017-00529
  3. https://www.federalregister.gov/d/2017-06625
  4. https://www.federalregister.gov/d/2019-28520