International edition
Nuclear News Network

Reporting the buildout, from mine to megawatt

NRC Licensing Review Tracker

Oklo Aurora custom combined license (INL)

Denied · Combined licence (COL) · New reactors

Oklo Aurora custom combined license (INL): NRC combined licence (col) review for Oklo Power LLC (subsidiary of Oklo Inc.) — denied, 19.1 months from docketing to decision. Sourced dates and schedule.

Background: NRC reactor licensing process, explained · The ADVANCE Act, explained: what changed and where the NRC stands

Current state

TypeCombined licence (COL)
OutcomeDenied
ApplicantOklo Power LLC (subsidiary of Oklo Inc.)
FacilityAurora (Idaho National Laboratory)
Docket52-049
Submitted2020-03-11
Docketed (accepted for review)2020-06-05
NRC planned schedule—
NRC target date—
Final safety evaluation—
Decision2022-01-06
Review time (docketed → decision)19.1 mo
Submitted → decision21.9 mo
NRC-reported review duration—
NRC-reported resources vs estimate—

Review time is measured in average months from the date the NRC docketed the application to the decision. The NRC's own reported durations may measure to the final safety evaluation instead.

Notes

Exclude from completed-review duration statistics (denial, not a decision on the merits). No new Oklo application found as of 2026-10-16: NRC pre-application page lists a 'Preapplication Readiness Assessment for Phase 1 of a Combined License Application' and a 'Pre-Phase 2 Combined License Application' audit, but no tendered application. Final safety evaluation: No safety evaluation issued (application denied). Decision: Denial letter dated January 6, 2022 (ML21357A034); denied without prejudice under 10 CFR 2.108 for failure to supply information.

Timeline

  • 2020-03-11 — Application received: “The application for the combined license was received on March 11, 2020.” (source)
  • 2020-06-05 — Accepted for review (docketed): “This action became effective on June 5, 2020.” (source)
  • 2022-01-06 — Denied: “The NRC staff has denied the custom combined license application” (source)

The timeline is append-only: corrections are added as new entries. See the NNN Data License Terms for reuse of the event history.

Also tracked

NNN coverage

About Oklo

Related reviews

See all 75 reviews in the NRC Licensing Review Tracker →

Sources

  1. https://www.nrc.gov/facilities-safety/new-reactors/large-light-water-reactors/combined-license-applications-for-new-reactors/aurora-oklo
  2. https://www.federalregister.gov/d/2020-06939
  3. https://www.federalregister.gov/d/2020-12903
  4. https://www.federalregister.gov/d/2022-00339
  5. https://www.nrc.gov/docs/ML2135/ML21357A034.pdf