Siberian Chemical Combine (SCC) isotope separation plant, Seversk

Operating · Russia · Enrichment plant

The enrichment (isotope separation) plant of Rosatom's Siberian Chemical Combine in Seversk, listed by WISE at a nominal 3 million SWU a year. In December 2025 Rosatom launched the first block of generation 9+ centrifuges there, the third of its four enrichment sites to modernize, with further blocks due to be commissioned through 2027.

New to HALEU and enrichment? HALEU, explained: the fuel advanced reactors need · The U.S. nuclear fuel supply chain, explained

Current state

StatusOperating
CountryRussia
LocationSeversk, Tomsk region
OperatorJSC Siberian Chemical Combine, TVEL / Rosatom
OwnershipRosatom (Russian state corporation) via its Fuel Division (TVEL).
Facility typeEnrichment plant
TechnologyGas centrifuge
ProductsLEU
Capacity (tSWU/yr)3,000

Notes

Capacity 3,000 tSWU/yr is WISE's nominal (dated) figure; modernization replaces centrifuges and may not change nameplate capacity, so no target capacity is given; 2027 is the modernization completion target. WNA (Sept 2026, from Nuclear Fuel Report 2025) gives Rosatom's combined capacity across all four sites as 29,133 tSWU/yr in 2025 (about 43% of world capacity), so WISE's dated per-plant figures understate the current total. Rosatom does not publish per-site capacity.

Timeline

  • 2017-10-16 — SCC completed dismantling two blocks of fifth-generation centrifuges, leaving sixth- to eighth-generation machines installed. (source)
  • 2025-12-02 — Rosatom launched the first block of generation 9+ centrifuges at the Seversk isotope separation plant, with further commissioning scheduled for 2025-2027. (source)

The timeline is append-only: corrections are added as new entries. Stated targets appear in the current-state table, never as milestones.

NNN coverage

About Rosatom

Related facilities

See all 29 facilities in the Uranium Enrichment & HALEU Tracker →

Sources

  1. Rosatom starts modernization of its third uranium enrichment plant — Rosatom (Atommedia) (primary), checked 2026-10-11
  2. Rosatom begins deployment of new-generation centrifuges at Seversk — International Panel on Fissile Materials, checked 2026-10-11
  3. Current Issues: Operating Uranium Conversion/Enrichment and Nuclear Fuel Plants - Russia — WISE Uranium Project, checked 2026-10-11