Current state
| Status | Under construction |
| Design | VVER-1200 (PWR) |
| Net capacity | 1,114 MWe |
| Country | Türkiye |
| Vendor | Rosatom |
| Owner / operator | Akkuyu Nuclear JSC (Rosatom BOO) |
| Construction start | 2020 |
| Original COD target | — |
| Current COD estimate | 2027 |
| Schedule slippage | — |
Notes
Verified 2026-09-22: NDK pre-commissioning permit May 2026 (WNN) and containment completed June 2026 (Akkuyu Nuclear). Unit tracking toward 2027 grid connection per WNA table; unit 1 construction completed June 2026 with fuel load planned fall 2026. Primary-circuit welding completed Aug 2026 (73-day weld, per Akkuyu Nuclear; NNN covered 2026-08-29) — operator-single-source, not asserted.
Milestone log
- 2026-06-16 — Listed as under construction in the WNA world table, grid connection estimated 2027 (source)
- 2026-01-08 — Turbine generator stator (437 t) installed at unit 2 (source)
- 2026-03-25 — Polar crane installed in unit 2 reactor building (source)
- 2026-05-07 — Turkey's nuclear regulator (NDK) granted pre-commissioning permit for unit 2 (source)
- 2026-06-29 — Reactor building containment completed at Akkuyu unit 2 (source)
The milestone log is append-only: corrections are recorded as new entries, never rewrites. Full history via /api/v1/changes.
NNN coverage
About Akkuyu-2
- Akkuyu 2 finishes primary-circuit welding in 73 days 2026-08-29
- Akkuyu 1 completes primary-circuit hydraulic tests 2026-10-10
- Vietnam picks Rosatom for Ninh Thuan 1, Korea closes on Ninh Thuan 2 2026-09-13
- Rosatom signs EPC contract for Kazakhstan's first nuclear plant 2026-09-04
- The 6 nuclear stories that mattered this week 2026-08-29