VVER-1200 · 1,114 MWe · Under construction · commercial operation est. 2028

Current state

StatusUnder construction
DesignVVER-1200 (PWR)
Net capacity1,114 MWe
CountryTürkiye
VendorRosatom
Owner / operatorAkkuyu Nuclear JSC (Rosatom BOO)
Construction start2022
Original COD target—
Current COD estimate2028
Schedule slippage—

Notes

Verified 2026-09-28: thrust truss Mar 2026 (Rosatom, operator-single-source) and turbine-hall slab Sep 2026 (Rosatom + DHA Turkish agency). 2028 grid connection per WNA table.

Milestone log

  • 2026-06-16 — Listed as under construction in the WNA world table, grid connection estimated 2028 (source)
  • 2026-03-13 — Thrust truss installed in unit 4 reactor compartment (source)
  • 2026-09-24 — Turbine-hall slab concreting completed (1,801 m3); foundation prep for the turbine generator begins next (Rosatom via DHA) (source)

The milestone log is append-only: corrections are recorded as new entries, never rewrites. Full history via /api/v1/changes.

NNN coverage

At Akkuyu Nuclear Power Plant

On the VVER-1200 design

Sources

  1. https://world-nuclear.org/information-library/current-and-future-generation/plans-for-new-reactors-worldwide
  2. https://pris.iaea.org/pris/
  3. https://rosatom-energy.ru/en/projects/akkuyu/