NuScale US460 standard design approval: NRC standard design approval review for NuScale Power, LLC — issued, 21.9 months from docketing to decision. Sourced dates and schedule.

Background: NRC reactor licensing process, explained · The ADVANCE Act, explained: what changed and where the NRC stands

Current state

TypeStandard design approval
OutcomeIssued
ApplicantNuScale Power, LLC
FacilityNuScale US460 (6 x 77 MWe modules, 462 MWe)
Docket52-050
Submitted2023-01-01
Docketed (accepted for review)2023-07-31
NRC planned schedule24 months
NRC target date—
Final safety evaluation2025-05-22
Decision2025-05-29
Review time (docketed → decision)21.9 mo
Submitted → decision28.9 mo
NRC-reported review duration22 months
NRC-reported resources vs estimate8% under

Review time is measured in average months from the date the NRC docketed the application to the decision. The NRC's own reported durations may measure to the final safety evaluation instead.

Notes

NRC target decision: 2025-07 (month only). Docketed pre-ADVANCE, decided post-ADVANCE. NRC page: 'Standard Design Approval (SDA) was issued in May of 2025 - two months ahead of schedule.' 22 executed months ~ docketing (2023-07-31) to FSER (2025-05-22). Submitted: Staged submittal: FR 2023-05457 'The SDA application was submitted in a number of transmittals between the period of November 23, 2022, and December 31, 2022.' and 'was available on January 1, 2023'. Docketed: Acceptance review took ~7 months (supplemental information requested).

Timeline

  • 2023-01-01 — Application received: “By letter dated December 31, 2022 (electronically submitted on January 1, 2023), NuScale completed its staged SDA application submittal.” (source)
  • 2023-07-31 — Accepted for review (docketed): “The NRC staff provided NuScale notice of the staff's determination that its application was acceptable for docketing by letter dated July 31, 2023” (source)
  • 2025-05-22 — Final safety evaluation issued. (source)
  • 2025-05-29 — Issued: “The SDA was issued on May 29, 2025.” (source)

The timeline is append-only: corrections are added as new entries. See the NNN Data License Terms for reuse of the event history.

NNN coverage

About NuScale US460 (VOYGR)

About NuScale Power

Related reviews

See all 75 reviews in the NRC Licensing Review Tracker →

Sources

  1. https://www.nrc.gov/facilities-safety/new-reactors/advanced-reactors/who-were-working-with/past-licensing-activities/nuscale-us460
  2. https://www.nrc.gov/facilities-safety/new-reactors/advanced-reactors/who-were-working-with/past-licensing-activities/nuscale-us460/application-documents
  3. https://www.federalregister.gov/d/2023-05457
  4. https://www.federalregister.gov/d/2023-16679
  5. https://www.federalregister.gov/d/2025-10123
  6. https://www.nrc.gov/regulations-legislation/effectiveness-efficiency-and-timeliness-initiatives-that-support-unleashing-american-energy/licensing-efficiencies