International edition
Nuclear News Network

Reporting the buildout, from mine to megawatt

NRC Licensing Review Tracker

NuScale US600 small modular reactor design certification

Issued · Design certification · Designs

NuScale US600 small modular reactor design certification: NRC design certification review for NuScale Power, LLC — issued, 71.3 months from docketing to decision. Sourced dates and schedule.

Background: NRC reactor licensing process, explained · The ADVANCE Act, explained: what changed and where the NRC stands

Current state

TypeDesign certification
OutcomeIssued
ApplicantNuScale Power, LLC
FacilityNuScale US600 (12 x 50 MWe modules)
Docket52-048
Submitted2017-01-06
Docketed (accepted for review)2017-03-15
NRC planned schedule—
NRC target date—
Final safety evaluation2020-08-28
Decision2023-02-21
Review time (docketed → decision)71.3 mo
Submitted → decision73.5 mo
NRC-reported review duration—
NRC-reported resources vs estimate—

Review time is measured in average months from the date the NRC docketed the application to the decision. The NRC's own reported durations may measure to the final safety evaluation instead.

Notes

Measuring to the FSER (2020-08-28) vs to the rule (2023) differs by ~2.5 years of rulemaking. Docketed and FSER pre-ADVANCE. Submitted: Transmittal letter dated December 31, 2016. Same FR notice's DATES line: 'The application was received on January 13, 2017.' (after electronic processing was completed January 12, 2017). NRC schedule page: 'Received design certification application | 01/06/17 – A'. Docketed: Conflict: NRC schedule page lists 'Issue acceptance letter to applicant | 03/23/17 – A'. Decision: Final rule certifying the design published in the Federal Register January 19, 2023 (88 FR 3287); decided.date = effective date of the certification rule.

Timeline

  • 2017-01-06 — Application received: “received a design certification application (DCA) from NuScale Power, LLC (NuScale), on January 6, 2017” (source)
  • 2017-03-15 — Accepted for review (docketed): “The U.S. Nuclear Regulatory Commission (NRC) has accepted for docketing an application for a design certification ... DATES: March 15, 2017.” (source)
  • 2020-08-28 — Final safety evaluation issued. (source)
  • 2023-02-21 — Issued: “This final rule is effective on February 21, 2023.” (source)

The timeline is append-only: corrections are added as new entries. See the NNN Data License Terms for reuse of the event history.

NNN coverage

About NuScale Power

Related reviews

See all 75 reviews in the NRC Licensing Review Tracker →

Sources

  1. https://www.nrc.gov/facilities-safety/new-reactors/advanced-reactors/who-were-working-with/past-licensing-activities/nuscale
  2. https://www.nrc.gov/facilities-safety/new-reactors/advanced-reactors/who-were-working-with/past-licensing-activities/nuscale/application-review-schedule
  3. https://www.federalregister.gov/d/2017-03438
  4. https://www.federalregister.gov/d/2017-06309
  5. https://www.federalregister.gov/d/2023-00729