Current state
| Type | Standard design approval |
| Outcome | Issued |
| Applicant | NuScale Power, LLC |
| Facility | NuScale US600 |
| Docket | 52-048 |
| Submitted | 2020-07-13 |
| Docketed (accepted for review) | — |
| NRC planned schedule | — |
| NRC target date | — |
| Final safety evaluation | 2020-08-28 |
| Decision | 2020-09-11 |
| Review time (docketed → decision) | — |
| Submitted → decision | 2.0 mo |
| NRC-reported review duration | — |
| NRC-reported resources vs estimate | — |
Review time is measured in average months from the date the NRC docketed the application to the decision. The NRC's own reported durations may measure to the final safety evaluation instead.
Notes
Derivative of the US600 DC review; exclude from duration statistics or treat as a 2-month administrative action. Docketed: Not separately docketed; the SDA request relied on the already-docketed DC review (FSER 2020-08-28). Final safety evaluation: Shared with the DC review.
Timeline
- 2020-07-13 — Application received: “July 13, 2020, submitted Request for Standard Design Approval ( [ML20195C766]) - approved September 11, 2020” (source)
- 2020-08-28 — Final safety evaluation issued. (source)
- 2020-09-11 — Issued: “The Standard Design Approval was issued on September 11, 2020.” (source)
The timeline is append-only: corrections are added as new entries. See the NNN Data License Terms for reuse of the event history.
NNN coverage
About NuScale Power
- Nuclear power for data centers, explained: every deal tracked 2026-10-01
- Singapore's nuclear future: policy, money and the industry map 2026-09-22
- Analysts size Africa's SMR market at $105B, 15 GW by 2035 2026-09-07
- Top SMR developers in 2026, ranked by what they've actually built 2026-08-05
- Small modular reactors, explained: who is building them worldwide 2026-07-09
Related reviews
- NuScale US460 standard design approval Issued · 21.9 mo
- NuScale US600 small modular reactor design certification Issued · 71.3 mo
See all 75 reviews in the NRC Licensing Review Tracker →
Sources
- https://www.nrc.gov/facilities-safety/new-reactors/advanced-reactors/who-were-working-with/past-licensing-activities/nuscale
- https://www.federalregister.gov/d/2020-21429
- https://www.nrc.gov/docs/ML2024/ML20247J564.pdf
- https://www.nrc.gov/facilities-safety/new-reactors/advanced-reactors/who-were-working-with/past-licensing-activities/nuscale/application-review-schedule