Kori Unit 1

Active dismantling · South Korea · Immediate dismantling

Kori 1, South Korea's first commercial reactor (576 MWe PWR, 1978), shut in June 2017 and in June 2025 became the country's first unit approved for dismantling. KHNP plans to move spent fuel to an on-site dry store by 2031 and finish in 2037 at an estimated cost of KRW 1.07 trillion.

New to decommissioning? The nuclear decommissioning market in 2026: size, players, pipeline

Current state

StatusActive dismantling
CountrySouth Korea
LocationGijang, Busan
SiteKori
UnitsUnit 1
Unit count1
Reactor typesPWR
Net capacity (MWe)576
Owner / licenseeKorea Hydro & Nuclear Power (KHNP)
StrategyImmediate dismantling
Final shutdown2017-06-18
Decommissioning start2025-06-26
Target completion2037
Cost estimateKRW 1071.3bn (as of 2025-06)
Spent fuelSpent fuel in the pool, to be moved to an on-site dry storage facility due for completion by 2031.
Notable issueNo interim or permanent spent-fuel store yet sited in Korea; first full commercial reactor dismantling in the country.

Notes

Capacity: WNN cites 576 MWe; JoongAng cites 587 MW (gross). Cost KRW 1.0713tn includes KRW 808.8bn decommissioning + KRW 252.5bn waste disposal.

Timeline

  • 1978-04-29 — Kori 1 began commercial operation. (source)
  • 2017-06-18 — Kori 1 was permanently shut down. (source)
  • 2021-05 — KHNP submitted its final decommissioning plan to the NSSC. (source)
  • 2024-05 — KHNP began preliminary chemical decontamination. (source)
  • 2025-06-26 — The Nuclear Safety and Security Commission approved Kori 1's decommissioning. (source)

The timeline is append-only: corrections are added as new entries. Stated targets appear in the current-state table, never as milestones.

NNN coverage

About Korea Hydro & Nuclear Power

Related sites

See all 72 sites in the Nuclear Decommissioning Tracker →

Sources

  1. Decommissioning of oldest Korean reactor approved — World Nuclear News, checked 2026-10-11
  2. Korea approves decommissioning of Kori-1, its first commercial nuclear reactor — Korea JoongAng Daily, checked 2026-10-11
  3. S. Korea approves decommissioning of Kori-1 nuclear reactor — Yonhap News Agency, checked 2026-10-11